Today we would like to share another inquiry on GN Soil Remediation Unit. Here are the questions from our customer:
1. Does this system need a Pre-screening (or shaker type system), in the event large solids get pulled from the Tunneling operations (i.e. clay clumps, sand, nuts bolts, grease clumps, etc.)?
It's necessary to use one coarse shaker before feeding the slurry into decanter centrifuge if you have those large solids. We actually recommend the coarse shaker before. By using a coarse shaker (double deck or single deck depends on the slurry analysis), it will improve the separating performance of the centrifuge and also protect the centrifuge without too much wear from those large solids. Decanter Centrifuge
According to your former email, there's no large solids, please kindly help to double check. After treated by the decanter centrifuge, only few finer solids are left in the slurry. You may use one Inclined Plate Clarifier to removal them before release into the sewers. Or you may just use one holding tank in order to save cost.
2. Can you send a flow drawing of the complete system that shows the components included and any components that are needed that are not included?
Let's work on the system design first. A typical treating system will include: coarse shaker (depend on whether exist large solids)+ decanter centrifuge (necessary)+ dosing unit (necessary)+ inclined plate clarifier/ holding tank (optional).
For the decanter centrifuge +dosing unit, you may check those former drawings we sent to you before. Flow drawing can be provided after we confirm on what treating equipment will be needed.
GN Solids Control decanter centrifuge also provide Vibration switch to protect the two main bearings (also bearing temperature sensor), they can be fixed on the centrifuge as following decanter centrifuge we provided to Baker Hughes. They can both be integrated into our VFD control panel. Usually, they are provided when customer demands them. We have no problem to add them into your future unit.